In the past month, construction works at Nam O Heritage have been executed consistently with a high level of commitment and responsibility, ensuring construction quality and planned progess. Detailed progress for each component is as follows:

SHOPHOUSE MOCK-UP

TIẾN ĐỘ DỰ ÁN tháng 05 NĂM 2025
TIẾN ĐỘ DỰ ÁN tháng 05 NĂM 2025

As of the end of November 2025, 02 mock-up shophouses are opened for operation. Meanwhile, all 04 mock-up shophouse units have been fully completed with interior installation, wall finishing, floor tiling, MEP and air conditioning system installation.

In December 2025, the construction team is expected to continue with interior design and furnishing installation, as well as completing the indoor and corridor areas for all mock-up shophouses.

SHOPHOUSE FOUNDATIONS – HOI AN & DA NANG ZONES

TIẾN ĐỘ DỰ ÁN tháng 05 NĂM 2025
TIẾN ĐỘ DỰ ÁN tháng 05 NĂM 2025

In November 2025, all shophouses in Hoi An Zone were completed with structural concrete works for the attic floor, and over 40% of shophouses were progressed with structural concrete works for the rooftop. The construction team is concurrently proceeding with the basement completion for all shophouses in Da Nang Zone.

In December 2025, all shophouses in Hoi An Zone are set to complete the rooftop slab, while over 40% of shophouses in Da Nang Zone are expected to undergo the completion of structural works for ground floor slab.

VILLA TECHNICAL INFRASTRUCTURE

TIẾN ĐỘ DỰ ÁN tháng 05 NĂM 2025
TIẾN ĐỘ DỰ ÁN tháng 05 NĂM 2025

In November 2025, over 60% of technical infrastructure systems for the villa zone, including the electrical system, water system, lighting system, fire safety, road and sidewalk system constructions were completed.

In December 2025, these systems are expected to continue progressing towards completion, while landscape and greenery work along the internal roads is being proceeded.

INDOCHINE EXPRESS LOUNGE – VILLA ZONE RECEPTION

TIẾN ĐỘ DỰ ÁN tháng 05 NĂM 2025
TIẾN ĐỘ DỰ ÁN tháng 05 NĂM 2025

In November 2025, the construction and development teams continued with completion for the Villa Reception, including inspection and fine-tuning in accordance with the design. Meanwhile, the construction of pedestrian walkways, surrounding green park facilities and landscape was being completed.

In December 2025, the construction is expected to be completed and handed over for official operation.