Over the past month, the construction team of Nam O Heritage has been putting full efforts into completing the key components, with commitment to meeting the set schedule. The detailed progress of each component is as follows:

SHOPHOUSE MOCK-UP

TIẾN ĐỘ DỰ ÁN tháng 05 NĂM 2025
TIẾN ĐỘ DỰ ÁN tháng 05 NĂM 2025

As of the end of July 2025, all 04 mock-up shophouse units have been fully completed with built-in interior and wooden floor installation, while finishing wall plastering and MEP system installation.

In August 2025, the construction team is expected to complete wall plastering and room partitioning for all 04 mock-up shophouses, MEP and air conditioning systems installation. Meanwhile, interior design and furnishing installation are in progress.

SHOPHOUSE FOUNDATIONS – PHASE 2A & 2B

TIẾN ĐỘ DỰ ÁN tháng 05 NĂM 2025
TIẾN ĐỘ DỰ ÁN tháng 05 NĂM 2025

In July 2025, over 60% of shophouses in Zone 2A (Hoi An Zone) were completed with structural concrete works for the 4th floor. The construction team is concurrently proceeding with foundation completion and installation of underground MEP pipelines for nearly 80% of shophouses in Zone 2B (Da Nang Zone).

In August 2025, all shophouses in Zone 2A are set to complete the 4th-floor slab, while 80% of shophouses in Zone 2B are expected to undergo waterproofing installation and completion of structural works for basement floor slab.

VILLA TECHNICAL INFRASTRUCTURE

TIẾN ĐỘ DỰ ÁN tháng 05 NĂM 2025
TIẾN ĐỘ DỰ ÁN tháng 05 NĂM 2025

In July 2025, the construction of technical infrastructure systems is currently in progress, including the electrical system, water system, lighting system, fire safety as well as the main road system construction.

In August 2025, these systems are expected to continue progressing towards completion.

INDOCHINE EXPRESS LOUNGE – VILLA ZONE RECEPTION

TIẾN ĐỘ DỰ ÁN tháng 05 NĂM 2025
TIẾN ĐỘ DỰ ÁN tháng 05 NĂM 2025

In July 2025, construction works such as exterior wall painting, installation of the recessed MEP system, floor leveling and tiling,... were completed. The construction of structural works for pedestrian walkways and the surrounding green park features are underway.

In August 2025, the construction is expected to be completed and handed over for official operation and commercial use.