Tiêu đề dự án Nam Ô - Cập nhật tiến độ tháng 04-2025

Key components of Nam O Heritage are currently being executed by the construction team with utmost focus and commitment to meeting the set schedule. The detailed progress of each component is as follows:

SHOPHOUSE MOCK-UP

As of the end of June 2025, all 04 mock-up shophouse units have been fully completed with exterior wooden railing system installation, along with the MEP system installation, including air conditioning system.

In July 2025, the construction team is expected to complete wall plastering and room partitioning for all 04 mock-up shophouses, while continuing with interior design and furnishing installation.

TIẾN ĐỘ DỰ ÁN tháng 05 NĂM 2025
TIẾN ĐỘ DỰ ÁN tháng 05 NĂM 2025

SHOPHOUSE FOUNDATIONS – PHASE 2A & 2B

In June 2025, 85% of shophouses in Zone 2A (Hoi An Zone) were completed with structural concrete works for the 3rd floor. The construction team is concurrently proceeding with foundation completion and installation of underground MEP pipelines for 60% of shophouses in Zone 2B (Da Nang Zone).

In July 2025, 65% of shophouses in Zone 2A are scheduled to complete the 4th-floor slab, while 60% of shophouses in Zone 2B are expected to undergo waterproofing installation and completion of structural works for basement floor slab.

TIẾN ĐỘ DỰ ÁN tháng 05 NĂM 2025
TIẾN ĐỘ DỰ ÁN tháng 05 NĂM 2025

VILLA TECHNICAL INFRASTRUCTURE

In June 2025, the construction of technical infrastructure systems is currently in progress, including the water drainage, electrical system, lighting system, fire safety as well as the main road system construction.

In July 2025, these systems are expected to continue progressing towards completion.

TIẾN ĐỘ DỰ ÁN tháng 05 NĂM 2025
TIẾN ĐỘ DỰ ÁN tháng 05 NĂM 2025

INDOCHINE EXPRESS LOUNGE – VILLA ZONE RECEPTION

In June 2025, wall plastering, floor leveling and installation of the recessed MEP lighting system were completed. Ceiling painting is underway, alongside the construction of structural works for pedestrian walkways and the surrounding green park features.

In July 2025, the construction team will continue with interior wall painting, floor tiling, glass partition installation, along with structural works for pedestrian walkways and the surrounding green park features.