Approaching the Lunar New Year, construction activities at Nam O Heritage are being executed continuously with a high level of professionalism and responsibility, ensuring both quality and progress as planned. Detailed progress for each component is as follows:
SHOPHOUSE MOCK-UP
As of the end of January 2026, 02 in 04 mock-up shophouses are being completed with interior installation. Meanwhile, structural works for floors, ceilings, walls, and technical system installation have been completed for 02 remaining units.
In February 2026, the construction team is expected to complete the installation of technical systems and furnishing for the indoor and corridor areas of all 04 units.
SHOPHOUSE FOUNDATIONS - HOI AN & DA NANG ZONES
In January 2026, over 50% of shophouses in Hoi An Zone were progressed with structural concrete works for the rooftop and finishing works for the seaside walkway. The construction team is concurrently proceeding with ground floor completion for over 60% of shophouses in Da Nang Zone.
In February 2026, all shophouses in Hoi An Zone are set to complete the rooftop slab, and all shophouses in Da Nang Zone are expected to undergo the completion of structural works for ground floor slab.
VILLA TECHNICAL INFRASTRUCTURE
In January 2026, over 90% of technical infrastructure systems for the villa zone, including the electrical system, water system, lighting system, fire safety, road and sidewalk system constructions were completed.
In February 2026, these systems are expected to continue progressing towards completion.
INDOCHINE EXPRESS LOUNGE – VILLA ZONE RECEPTION
In January 2026, the construction team has completed with villa reception construction and put into operation, introducing a new space of experience for our valued guests to welcome the Lunar New Year – Year of the Horse.