CONSTRUCTION UPDATE NAM O HERITAGE - MARCH 2025

The key components of the Nam O Heritage are being carried out by the construction team in accordance with the set schedule. The detailed progress is as follows:

SHOPHOUSE MOCK-UP

By the end of February 2025, all 4/4 mock-up shophouse units have had their balconies fully tiled, and 50% of the interior flooring has been completed.

In March 2025, all doors and flooring work are expected to be completed, allowing for the continuation of interior design and furnishing for the mock-up shophouse on the next floors.

CONSTRUCTION UPDATE NAM O HERITAGE - MARCH 2025
CONSTRUCTION UPDATE NAM O HERITAGE - MARCH 2025

SHOPHOUSE FOUNDATIONS - PHASE 2A & 2B

In February 2025, concrete was poured for the ground floor structural beams and slabs of 40 shophouses in zone 2A. Meanwhile, site preparation and equipment mobilization for zone 2B are underway.

In March 2025, the construction team is set to proceed with sheet piling and foundation excavation for the basement of zone 2B.

CONSTRUCTION UPDATE NAM O HERITAGE - MARCH 2025
CONSTRUCTION UPDATE NAM O HERITAGE - MARCH 2025

VILLA TECHNICAL INFRASTRUCTURE - PHASE 1

In February 2025, the developer completed the detailed design for the roads in Phase 2 and the entire villa area.

By March 2025, the design is expected to be finalized, and temporary construction work will begin to facilitate the next phases.

CONSTRUCTION UPDATE NAM O HERITAGE - MARCH 2025
CONSTRUCTION UPDATE NAM O HERITAGE - MARCH 2025

INDOCHINE EXPRESS LOUNGE - VILLA ZONE RECEPTION

In February 2025, the main structural framework was completed, and wall plastering began.

By March 2025, the exterior plastering will be finished, along with the construction of the connecting entrance structures.

CONSTRUCTION UPDATE NAM O HERITAGE - MARCH 2025
CONSTRUCTION UPDATE NAM O HERITAGE - MARCH 2025